Singapore’s huge, luxury resort, Marina Bay Sands, is undergoing a massive $1.75 billion renovation of its existing hotel towers and sky park.

In addition, an $8 billion new construction project for a fourth hotel tower and a huge entertainment center have been launched.  The new construction project is due to be completed in June of 2030.


Video Spotlight:  


This post is based on The Straits Times article, Las Vegas Sands flags $10.6b investment to develop fourth tower at Marina Bay Sands, by Ranamita Chakraborty, October 24, 2024, and the YouTube videos in the Spotlight. Image source: Viktor Posnov / Alamy Stock Photo

Discussion Questions:

1. What challenges have arisen since the project began?

Guidance: It is often the case in project management that timelines and costs change during the course of the project.  Back in 2019, the cost of the project was estimated to be $3.3 billion, including the cost of the land.  Since then, cost projections have more than doubled to $8 billion.  Reasons include inflation, issues that occurred because of the pandemic, and rising costs for material and labor.

2.  What is the timeline for project completion?

Guidance: At this point, construction on the 4th tower and arena project is scheduled to begin in June of 2025.  In April 2024, the projected completion date was July 2029.  As of October 2024, the completion date was pushed out to June 2030. Thus, before the project has even begun, its timeline has lengthened.

Project managers can use probabilistic time estimates to figure the likelihood that a project will be completed within various amounts of time. Completion dates are not a certainty.

Projects often run into unexpected difficulties once they are underway as well.  This may include delays related to weather, permitting issues, failed inspections, and the availability of materials, equipment, and labor.  When that happens, project managers have to make important decisions about whether or not to try to spend more money to speed project completion, if that is even possible, or miss the deadline for completion.

Spending extra money to speed up certain activities is known as “crashing.” Candidates for crashing will be activities on the critical path of the project.  Crashing activities that are not on the critical path will not improve the project completion date.  Missing completion deadlines can create a host of other problems as well as delaying the inflow of revenue from the hotel and entertainment centers themselves, and any tentative bookings may have to be cancelled or rescheduled.